  1. When does the lessor’s DLP ends and date to handover back?
  2. Which version of the Design brief did the lessor follow?
  3. Which version of the BCA did the lessor follow, 2016 or 2019
  4. We will require the complete O&M and As-built drawings, for example clause #3.3.58 stated that laminated drawings will need to be provided within 4 weeks of Practical Completion. Please refer to Detailed Requirements for more details.
as-built
5. The O&M must include pdf drawings and its source file (Autocad and/or Revit), testing, commissioning records. The BMS functional Design Specifications must include the below
• System architecture drawings
• Controls Point lists
• Controls Wiring diagrams
• Controls Commissioning sheet
• Admin credentials
• Disaster backups

6. We will need to verify among the many items such as the below
• Lighting scheduling
• Plant equipment alarm settings
• Temperature setpoint
• Sensor fault notification settings
• Chiller operation strategies
• UI time clock (WST)
• UI alarms & enunciation
• UI schedule access
• UI audit trails to log user activities